Current Work Overview
Real-time snapshot of YeboLearn's active development work, team capacity, and sprint progress. Updated daily during standup.
Last Updated: November 22, 2025 - Sprint 26, Day 4
Current Sprint Status
Sprint 26 (November 18 - November 29)
Sprint Goal: Launch AI Essay Grading Beta & M-Pesa Integration
Progress:
Committed: 32 story points
Completed: 14 story points (44%)
In Progress: 13 story points (41%)
Not Started: 5 story points (15%)
Days Remaining: 6 days
On Track: Yes ✓Burndown:
Day 0 (Nov 18): 32 points remaining
Day 1 (Nov 19): 32 points remaining (planning complete)
Day 2 (Nov 20): 28 points remaining (4 points completed)
Day 3 (Nov 21): 23 points remaining (9 points completed)
Day 4 (Nov 22): 18 points remaining (14 points completed)
Ideal Burndown: 18 points
Actual: 18 points (perfectly on track)Active Features in Development
1. AI Essay Grading (21 points total, 65% complete)
Status: In Progress, On Track Target: Sprint 26 Release (Nov 29) Owner: Sarah (UI), John (Backend), Lisa (Testing)
Completed:
- ✅ Essay submission interface (9 pts)
- ✅ Database schema and migrations (2 pts)
- ✅ Gemini API integration (3 pts)
In Progress:
🚧 AI feedback generation and display (5 pts) - 80% done
- Real-time feedback rendering complete
- Working on revision history tracking
- Expected completion: Nov 23
🚧 Teacher review dashboard (5 pts) - 70% done
- Submission list view complete
- Grade override in progress
- Expected completion: Nov 24
Not Started:
- ⏳ Rate limiting and caching (2 pts)
- Scheduled to start: Nov 24
- Expected completion: Nov 25
Risks:
- ⚠️ Gemini API response time averaging 45s (target: 30s)
- Mitigation: Investigating caching strategy
- Impact: May need optimization spike in Sprint 27
Dependencies:
- ✅ Gemini API quota increased (completed Nov 20)
- ✅ Design specs for teacher dashboard (delivered Nov 19)
2. M-Pesa Payment Integration (13 points total, 40% complete)
Status: In Progress, On Track Target: Sprint 26 Release (Nov 29) Owner: Mark (Lead), Lisa (Testing)
Completed:
- ✅ M-Pesa API credentials and sandbox setup (1 pt)
- ✅ Payment initiation endpoint (3 pts)
In Progress:
- 🚧 Webhook callback handling (5 pts) - 50% done
- Callback verification complete
- Working on database updates
- Expected completion: Nov 25
Not Started:
⏳ Error recovery and retry logic (3 pts)
- Scheduled to start: Nov 25
- Expected completion: Nov 27
⏳ Payment status dashboard (1 pt)
- Scheduled to start: Nov 27
- Expected completion: Nov 28
Risks:
- None currently
Dependencies:
- ✅ M-Pesa sandbox access granted
- ⏳ Production credentials (expected Nov 26)
3. API Performance Optimization (5 points total, 20% complete)
Status: In Progress, Stretch Goal Target: Sprint 26 or Sprint 27 Owner: Sarah
Completed:
- ✅ Performance baseline measurements (1 pt)
In Progress:
- 🚧 Database query optimization (3 pts) - 20% done
- Added indexes on student_id, course_id
- Testing query performance improvements
- Expected completion: Nov 26
Not Started:
- ⏳ Redis caching implementation (1 pt)
- May defer to Sprint 27 if capacity tight
Current Metrics:
- Dashboard load time: 2.2s → 1.9s (target: <1.5s)
- API p95 response time: 450ms → 380ms (target: <200ms)
4. Bug Fixes (3 points total, 100% complete)
Status: Complete ✅ Owner: Team
Completed:
- ✅ Fixed login redirect after signup (1 pt)
- ✅ Resolved quiz timer accuracy issue (1 pt)
- ✅ Fixed mobile responsiveness on quiz page (1 pt)
Team Capacity
Current Team (Sprint 26)
Sarah - Frontend Lead
Capacity: 100% (no PTO, no interruptions)
Allocated:
- Essay feedback UI (5 pts) - In Progress
- Performance optimization (4 pts) - In Progress
Total: 9 points
Completed This Sprint: 11 points
Velocity: On TrackJohn - Backend Lead
Capacity: 100%
Allocated:
- AI grading backend (8 pts) - 75% Complete
Total: 8 points
Completed This Sprint: 5 points
Velocity: On TrackLisa - Full Stack
Capacity: 90% (On-call rotation this week)
Allocated:
- Teacher dashboard (5 pts) - In Progress
- M-Pesa testing (3 pts) - Not Started
Total: 8 points
Completed This Sprint: 4 points
Velocity: On Track
Note: Handled 2 production incidents (minor, 30 min each)Mark - Backend/Integrations
Capacity: 100%
Allocated:
- M-Pesa integration (13 pts) - In Progress
Total: 13 points
Completed This Sprint: 4 points
Velocity: On TrackTotal Team Capacity: 390% (3.9 developers) Committed Work: 32 points (within velocity range)
Upcoming Availability
Next Week (Sprint 26 Week 2):
- All team members available
- No planned PTO
- On-call: John (rotation)
Sprint 27 (Dec 2 - Dec 13):
- Mark: PTO Dec 5-6 (2 days)
- Adjusted capacity: ~30 points
Holiday Planning:
- Christmas week (Dec 23-27): Reduced sprint
- New Year's week (Dec 30 - Jan 3): Reduced sprint
Blockers and Risks
Current Blockers
None - All blockers resolved! 🎉
Recent resolutions:
- ✅ Gemini API quota (resolved Nov 20)
- ✅ Teacher dashboard design (delivered Nov 19)
- ✅ M-Pesa sandbox access (granted Nov 18)
Active Risks
Risk 1: AI Response Time Performance
Impact: Medium
Probability: Medium
Description: Gemini API averaging 45s response time (target: 30s)
Mitigation:
- Investigating caching strategy
- Exploring prompt optimization
- May add performance spike to Sprint 27
Owner: John
Status: MonitoringRisk 2: M-Pesa Production Credentials Delay
Impact: High (blocks production launch)
Probability: Low
Description: Production credentials expected Nov 26, but not confirmed
Mitigation:
- Following up daily with M-Pesa team
- Sandbox fully functional as backup
- Can launch beta without production credentials
Owner: Mark
Status: Monitoring, following upRisk 3: Sprint 27 Capacity (Holiday Season)
Impact: Low
Probability: High
Description: Team velocity may decrease in December (holidays, year-end)
Mitigation:
- Plan Sprint 27-28 conservatively (25-28 points)
- Front-load critical work in Sprint 27
- Defer nice-to-haves to January
Owner: Team Lead
Status: Planned forProduction Health
System Status
Uptime: 99.97% (last 30 days) Incidents This Sprint: 2 (both minor, resolved <1 hour)
Recent Incidents:
Nov 21, 10:30 AM - Database connection spike
Severity: P2 (Medium)
Duration: 20 minutes
Resolution: Restarted connection pool, added monitoring alert
Impact: ~50 users experienced slow page loads
Nov 19, 3:15 PM - Quiz submission timeout
Severity: P2 (Medium)
Duration: 45 minutes
Resolution: Optimized quiz save query, added index
Impact: ~20 users unable to submit quizzes temporarilyPerformance Metrics (Last 7 Days)
API Response Time:
- p50: 145ms (target: <200ms) ✓
- p95: 380ms (target: <500ms) ✓
- p99: 820ms (target: <1s) ✓
Page Load Time:
- Dashboard: 1.9s (target: <2s) ✓
- Quiz Page: 1.2s (target: <2s) ✓
- Course Page: 1.6s (target: <2s) ✓
Error Rate:
- API Errors: 0.3% (target: <1%) ✓
- Frontend Errors: 0.1% (target: <0.5%) ✓
Active Users:
- Daily Active: 2,340 (↑12% from last week)
- Peak Concurrent: 180 usersDeployment Status
Last Deployment: Nov 21, 10:00 AM (Sprint 26, Day 3) Next Deployment: Nov 29, 10:00 AM (Sprint 26 Release)
Deployed Features (This Sprint):
- Essay submission interface
- Bug fixes (login redirect, quiz timer, mobile UI)
- Performance improvements (query optimization)
Pending Deployment (End of Sprint):
- AI essay grading (complete feature)
- M-Pesa integration
- Additional performance optimizations
Sprint Forecast
Will We Hit Our Sprint Goal?
Sprint Goal: Launch AI Essay Grading Beta & M-Pesa Integration
Confidence Level: 85% (High Confidence)
Analysis:
AI Essay Grading:
- 65% complete with 6 days remaining
- On track for completion
- Minor performance concern (response time)
- Overall: 90% confident ✓
M-Pesa Integration:
- 40% complete with 6 days remaining
- Backend work on track
- Waiting on production credentials (not blocking beta)
- Overall: 80% confident ✓
Stretch Goals (Performance):
- May partially complete
- Can defer remaining work to Sprint 27
- Overall: 60% confident (stretch goal, acceptable)Adjustments:
- None needed, sprint on track
- Continue monitoring AI performance
- Daily check-ins on M-Pesa credentials
Upcoming Work (Sprint 27 Preview)
Tentative Sprint 27 (Dec 2 - Dec 13)
Planned Features:
- WhatsApp notification integration (8 pts)
- AI performance optimization (5 pts)
- Student progress certificates (5 pts)
- Offline mode spike (3 pts)
- Bug fixes and polish (5 pts)
Total: ~26 points (conservative for holidays)
Dependencies:
- WhatsApp Business API access (applied, pending)
- Certificate design templates (in progress)
Daily Updates
November 22, 2025 (Day 4)
Completed Yesterday:
- ✅ Essay feedback rendering (Sarah)
- ✅ M-Pesa payment initiation testing (Mark)
- ✅ Database query optimization (Sarah)
Shipping Today:
- 🚧 Revision history tracking (Sarah)
- 🚧 Teacher dashboard grade override (Lisa)
- 🚧 M-Pesa webhook database updates (Mark)
Blockers:
- None
Team Notes:
- John investigating Gemini API performance
- Lisa on-call, handled minor DB connection issue
- Sarah ahead of schedule on performance work
Team Morale
Current Sprint Satisfaction: 8/10
Positives:
- ✓ Clear sprint goal and priorities
- ✓ Good collaboration and pairing
- ✓ Minimal interruptions
- ✓ Features coming together well
Areas for Improvement:
- △ AI performance concern (being addressed)
- △ Some PR review delays (improved since Monday)
Communication
Stakeholder Updates
Last Update Sent: Nov 21 (Weekly Email) Next Update: Nov 28 (Pre-Release Briefing)
Key Messages:
- AI Essay Grading on track for Nov 29 launch
- Beta will include 100 students, 5 teachers
- M-Pesa integration ready for sandbox testing
- Performance improvements showing results
Demos
Next Demo: Nov 28, 3 PM (Sprint Review) Attendees: Engineering, Product, Design, Stakeholders
Demo Plan:
- AI Essay Grading (Sarah & John - 15 min)
- M-Pesa Integration (Mark - 10 min)
- Performance Improvements (Sarah - 5 min)
- Metrics & Impact (Product - 5 min)
- Q&A (10 min)
Quick Links
- AI Features Roadmap - Detailed AI development status
- Platform Improvements - Infrastructure and optimization work
- Integration Work - Third-party service integrations
- Sprint Planning - Sprint structure and ceremonies
- Development Workflow - Day-to-day processes